Small Cities Block Grant

The County Commission approved the 2015-2016 Small Cities Black Grant Application for the Elkins Road PSD III Waterline Extension during the April 23rd Commission Meeting.  The proposed Phase III Water Systems Improvements Project Waterline Extensions would serve approximately 91 customers, with 82 being new customers.  Additionally, the Phase III project includes installing stationery generators, tank rehabilitation, and the construction of a new office / maintenance building.  The total cost of the project is $6,488,000 with $1,500,000 as proposed funding from the Small Cities Block Grant.   This is the 7th year applying for the Small Cities Block Grant.  The application must be submitted by May 21, 2015, and Region VII Director Shane Whitehair requests that the public provide any feedback of problems to be included in the application.